New Castle Fire District No.1

 
 

Upcoming Events

03/31/2025
Project Meeting with Contractors (weekly)

04/07/2025
Project Meeting with Contractors (weekly)

04/14/2025
Board of Commissioners Project Special OACM Meeting

04/14/2025
Project Meeting with Contractors (weekly)

04/21/2025
Project Meeting with Contractors (weekly)

04/23/2025
Board of Commissioners Regular Meeting

04/28/2025
Project Meeting with Contractors (weekly)

View All Events


Web Counters
Website Visitors
Since
March 15, 2023
271,812
Visitors Today
Mar 31, 2025
18
Construction Update 2.12.25
Email Print RSS Facebook Twitter RSS

By Secretary CHRISTINE DENNETT
February 12, 2025

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

The New Castle Fire District No. 1 Modernization Project continues to make substantial progress, with key construction activities advancing as scheduled.

Key Updates Include:

Backfilling Operations and Site Work:

•Backfilling operations are ongoing, with the apparatus bay now completed. The back portion of the west retaining wall is being backfilled, and the east foundation area has also been backfilled following the successful 7-day concrete breaks. Plumbing and electrical contractors are on-site and laying out their underground work.
•The waterproofing vendor has added an additional 2 inches of insulation to the top portion of the previously completed waterproofing work behind the west retaining wall and the southwest retaining wall.
•The site contractor is focusing on ongoing site backfilling and excavation in preparation for the steel contractors to begin their work.

Cold Weather Plan:

•A cold weather plan remains in place to ensure that construction work, including concrete pouring, continues without delays despite adverse weather conditions.

Environmental Safety Measures:

•Silt fences have been installed to manage erosion and runoff, while silt baskets are in place to capture sediment and protect nearby stormwater systems.

Coordination with Contractors:

•Sewer Line Repair Work: Discussions are ongoing with the Town regarding permits for sewer line repair work. Materials are being procured for bracing to support excavation for this work.
•Electrical Work: The electrical contractor continues conduit connection work on-site at the southeast corner of the site.
•Plumbing Work: The plumbing contractor is expected to complete underground plumbing work, with 2 weeks estimated for completion of plumbing installation on the west side of the site.
•Masonry Work: The mason is scheduled to begin setting up for masonry work starting March 10th to begin the interior Concrete Masonry Unit (CMU) wall work below the future mezzanine area in preparation for the steel contractor.
•Steel Installation: The steel contractor is scheduled to mobilize and begin steel installation on March 3rd. The precast mezzanine deck is set for pickup in late February, and the steel contractor will use a crane for installation once the steel work progresses.

Logistics and Access:

•No parking is allowed on Elm Street or Memorial Drive, and deliveries must enter via King Street. Any access through Memorial Drive will be communicated to the team in advance.
•We are making excellent progress with the work out of sequence, enabling tasks like masonry and underground plumbing to be completed ahead of schedule.

The community is encouraged to stay informed through the Fire District’s website and local announcements as the project progresses. Regular updates on the project timeline, traffic impacts, and other developments will be shared. The Fire District welcomes community feedback and will continue to provide updates throughout the construction phase.

For more information, please contact the New Castle Fire District No. 1 Project Committee at project@ncfd1.org.

Stay tuned for further updates on this essential community enhancement project!


Add a Comment Add a Comment 0 Comment(s)


Website Designed and Hosted By: Content Proudly Maintained By: Contact Info:
Firehouse Solutions
www.FirehouseSolutions.com
New Castle Fire District No.1
491 King Street
Chappaqua, NY 10514
Emergency Dial 911
Non-Emergency: 914-238-6287
E-mail: bofc@ncfd1.org
Copyright © 2025 Firehouse Solutions (A Service of Technology Reflections, Inc.)