New Castle Fire District No.1

 
 

Upcoming Events

01/02/2025
Annual Organizational Meeting

01/02/2025
Executive Session

View All Events


Web Counters
Website Visitors
Since
March 15, 2023
233,168
Visitors Today
Dec 26, 2024
177
Construction Update 12.10.24
Email Print RSS Facebook Twitter RSS

By Secretary CHRISTINE DENNETT
December 10, 2024

New Castle Fire District No. 1 Modernization Project Update: Excavation, Formwork, and Concrete Pouring Underway
Chappaqua, NY

The New Castle Fire District No. 1 Modernization Project is progressing with key activities moving forward.

Key Updates Include:

•Excavation Work: Excavation has been completed along the southwest portion of the site, with ongoing excavation along the western section to prepare for footings and foundation work.
•Formwork Installation: Formwork installation is set to begin shortly. These materials are critical for the structural preparation of the foundation.
•Concrete Pouring: A total of 94 cubic yards of concrete has been poured along the southwest portion of the new foundation. Additional concrete pours will continue, with work scheduled to form a retaining wall along the west side of the new addition. A total of 9 concrete trucks have delivered material to the site so far.
•Cold Weather Plan: A cold weather plan is in place to ensure construction activities, including concrete pouring, proceed without delay despite potential weather challenges.
•Environmental Safety Measures: Silt fences will be installed to manage erosion and runoff, with silt baskets placed to catch sediment and protect nearby stormwater systems. A tracking pad will also be set up at the site entrance to prevent soil from being tracked onto surrounding roads.

Community members are encouraged to stay informed via the Fire District's website and local announcements as the project progresses. Regular updates on the project timeline, traffic impacts, and other developments will be provided. The fire district welcomes community feedback and will continue to share updates throughout the construction phase.

For more information, please contact the New Castle Fire District No. 1 Project Committee at project@ncfd1.org.

Stay tuned for further updates on this vital community enhancement project!


Add a Comment Add a Comment 0 Comment(s)


Website Designed and Hosted By: Content Proudly Maintained By: Contact Info:
Firehouse Solutions
www.FirehouseSolutions.com
New Castle Fire District No.1
491 King Street
Chappaqua, NY 10514
Emergency Dial 911
Non-Emergency: 914-238-6287
E-mail: bofc@ncfd1.org
Copyright © 2024 Firehouse Solutions (A Service of Technology Reflections, Inc.)