National Weather Service Alerts for Westchester County, NY
Welcome to New Castle Fire District No.1


he New Castle Fire District No. 1 is a political subdivision of the State. A Board of five Fire Commissioners governs the District. Residents of the Fire District elect Fire Commissioners. Each Commissioner is elected to a five-year term. Certain situations may occur where the Board can appoint an individual to fill a vacated position. Fire District Elections are held on the second Tuesday of December each year. One Commissioner is elected each year so that there will always be experienced Commissioners on the Board. The Fire District has a myriad of statutory responsibilities including the levying of taxes for the purpose of providing fire protection for the residents of the District. The Fire District budget is used to provide the Chappaqua Fire Department the funding necessary for equipment, apparatus, training, day-to-day operations, maintenance and repair of District facilities, amongst other specialty matters.
|
Construction Update 6.4.25
Secretary CHRISTINE DENNETT, June 04
New Castle Fire District No. 1 Modernization Project Update Chappaqua, NY
Key Updates
Progress and Coordination • Excavation equipment has been mobilized and soil removal is underway. • Block work is in progress in preparation for the precast mezzanine installation. • A crane and steel installation crew will begin installing the precast mezzanine deck, which is expected to take approximately two ... (Full Story)
|
Construction Update 5.27.25
Secretary CHRISTINE DENNETT, May 27
New Castle Fire District No. 1 Modernization Project Update Chappaqua, NY
Key Updates
Progress and Coordination • Excavation equipment was mobilized today, and soil removal is scheduled to begin on Wednesday, 5/28. • Block work is underway and expected to be completed this week in preparation for the upcoming precast mezzanine installation. • A crane and steel installation crew are scheduled to ... (Full Story)
|
Construction Update 5.19.25
Secretary CHRISTINE DENNETT, May 19
New Castle Fire District No. 1 Modernization Project Update Chappaqua, NY
Key Updates
Progress and Coordination
Masonry Work (Updated!) Block work will continue throughout the week, with masonry teams fully mobilized on site. The mason has started work on the southwest portion of the project, near the elevator, fill station, and shower area.
Mechanical, Electrical, Plumbing, and Fire Protection ... (Full Story)
|
|
Construction Update 5.14.25
Secretary CHRISTINE DENNETT, May 14
New Castle Fire District No. 1 Modernization Project Update Chappaqua, NY
Key Updates
Progress and Coordination
Steel Installation (Updated!) Steel erection is progressing steadily, officially taking the project vertical. This week, crews are focusing efforts on the west side of the project, working on completing bolted connections between steel beams and columns, installing metal decking on the ... (Full Story & Photos)
|
Construction Update 5.7.25
Secretary CHRISTINE DENNETT, May 07
New Castle Fire District No. 1 Modernization Project Update Chappaqua, NY
Key Updates:
Progress and Coordination: • Steel Installation (Updated!): Steel erection is underway, officially taking the project vertical. Work includes fall fittings, completing bolted connections between steel beams and columns, installing metal decking, and ensuring all beams are level. • Masonry Work (New!): The mason ... (Full Story)
|
|
Construction Update 4.30.25
Secretary CHRISTINE DENNETT, April 30
New Castle Fire District No. 1 Modernization Project Update Chappaqua, NY
Key Updates:
Progress and Coordination:
•Crane & Steel Installation (New!):
Exciting milestone — the crane has been delivered, and the first steel has been installed, officially taking the project vertical! Steel erection, including fall protection fittings, will continue on the west side of the site.
•Masonry Work (New!):
Masonry ... (Full Story & Photos)
|
Construction Update 4.22.25
Secretary CHRISTINE DENNETT, April 22
New Castle Fire District No. 1 Modernization Project Update Chappaqua, NY
Key Updates:
Progress and Coordination:
Plumbing Work:
•Backfilling the plumbing pipes with stone in all areas where electrical conduits are not being installed.
Electrical Work:
•Installation of the electrical conduit is scheduled to begin. An inspector is confirmed to be onsite tomorrow, Tuesday, 04/23 at 9:30 AM, to ... (Full Story)
|
Construction Update 4.8.25
Secretary CHRISTINE DENNETT, April 08
New Castle Fire District No. 1 Modernization Project Update Chappaqua, NY
Key Updates:
Progress and Coordination: • Plumbing Work: The plumbing work in the laundry and shower rooms has been completed. An inspection was conducted, and the system was successfully pressure tested by the Town. Additionally, a survey of the pipes is currently underway. The surveyor is onsite today, and the survey work ... (Full Story)
|
Your feedback is important to us! Feel free to sign the guestbook.
|