New Castle Fire District No.1

 
 

Upcoming Events

There are currently no events
View All Events


Web Counters
Website Visitors
Since
March 15, 2023
270,662
Visitors Today
Mar 28, 2025
58

Welcome to New Castle Fire District No.1


he New Castle Fire District No. 1 is a political subdivision of the State. A Board of five Fire Commissioners governs the District. Residents of the Fire District elect Fire Commissioners. Each Commissioner is elected to a five-year term. Certain situations may occur where the Board can appoint an individual to fill a vacated position. Fire District Elections are held on the second Tuesday of December each year. One Commissioner is elected each year so that there will always be experienced Commissioners on the Board. The Fire District has a myriad of statutory responsibilities including the levying of taxes for the purpose of providing fire protection for the residents of the District. The Fire District budget is used to provide the Chappaqua Fire Department the funding necessary for equipment, apparatus, training, day-to-day operations, maintenance and repair of District facilities, amongst other specialty matters.

Divider
Construction Update 3.26.25

Secretary CHRISTINE DENNETT, March 26

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates:

Progress and Coordination:

•Plumbing Work: The plumbing contractor is continuing with underground work in the laundry and shower rooms. Some of the previously installed piping was not pitched correctly due to the rain, but the plumber is correcting the issue today. Once completed, the plumbing system will be ... (Full Story)


Divider
Construction Update 3.17.25

Secretary CHRISTINE DENNETT, March 17

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates:

Site Dewatering and Weather Impact:

•The contractor is currently dewatering the site following the heavy rain over the weekend. A plan has been requested to address areas that continue to accumulate water. Gravel placement will need to be opened up for inspection and approval by the Town before the plumber can ... (Full Story)


Divider
Construction Update 3.12.25

Secretary CHRISTINE DENNETT, March 12

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates Include:

Backfilling Operations and Site Work:

•Backfilling operations are ongoing, with the plumbing and electrical contractors working to lay out their underground systems. The site contractor is focused on site backfilling and excavation in preparation for the steel contractors.
•Heavy rains have caused delays, ... (Full Story)


Divider
Construction Update 3.5.25

Secretary CHRISTINE DENNETT, March 05

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates Include:

Backfilling Operations and Site Work:

•Backfilling operations are ongoing, with progress continuing on-site. The plumbing and electrical contractors are currently working to lay out their underground systems. The site contractor is focused on site backfilling and excavation to prepare for the steel contractors ... (Full Story)


Divider
Construction Update 2.24.25

Secretary CHRISTINE DENNETT, February 24

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates Include:

Backfilling Operations and Site Work:

•Backfilling operations are ongoing. Plumbing and electrical contractors will be back on-site and laying out their underground work, which was delayed due to weather and freezing temperatures. The excavation contractor is back on-site after weather delays caused ... (Full Story)


Divider
Construction Update 2.18.25

Secretary CHRISTINE DENNETT, February 18

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

The New Castle Fire District No. 1 Modernization Project continues to make substantial progress, with key construction activities advancing as scheduled.

Key Updates Include:

Backfilling Operations and Site Work:

•Backfilling operations are ongoing, with the apparatus bay now completed. Plumbing and electrical contractors ... (Full Story)


Divider
Construction Update 2.12.25

Secretary CHRISTINE DENNETT, February 12

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

The New Castle Fire District No. 1 Modernization Project continues to make substantial progress, with key construction activities advancing as scheduled.

Key Updates Include:

Backfilling Operations and Site Work:

•Backfilling operations are ongoing, with the apparatus bay now completed. The back portion of the west retaining ... (Full Story)


Divider
Construction Update 2.5.25

Secretary CHRISTINE DENNETT, February 05

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

The New Castle Fire District No. 1 Modernization Project continues to make substantial progress, with essential construction activities advancing as planned.

Key Updates Include:

Backfilling Operations and Site Work:

•Backfilling operations are ongoing, with the apparatus bay now completed. The back portion of the west retaining ... (Full Story)


Divider

Your feedback is important to us!  Feel free to sign the guestbook.


Website Designed and Hosted By: Content Proudly Maintained By: Contact Info:
Firehouse Solutions
www.FirehouseSolutions.com
New Castle Fire District No.1
491 King Street
Chappaqua, NY 10514
Emergency Dial 911
Non-Emergency: 914-238-6287
E-mail: bofc@ncfd1.org
Copyright © 2025 Firehouse Solutions (A Service of Technology Reflections, Inc.)