New Castle Fire District No.1

 
 

Upcoming Events

06/16/2025
Project Meeting with Contractors (weekly)

06/18/2025
Board of Commissioners Regular Meeting

06/23/2025
Project Meeting with Contractors (weekly)

06/30/2025
Project Meeting with Contractors (weekly)

View All Events


Web Counters
Website Visitors
Since
March 15, 2023
309,024
Visitors Today
Jun 10, 2025
195
National Weather Service Alerts for Westchester County, NY

Welcome to New Castle Fire District No.1


he New Castle Fire District No. 1 is a political subdivision of the State. A Board of five Fire Commissioners governs the District. Residents of the Fire District elect Fire Commissioners. Each Commissioner is elected to a five-year term. Certain situations may occur where the Board can appoint an individual to fill a vacated position. Fire District Elections are held on the second Tuesday of December each year. One Commissioner is elected each year so that there will always be experienced Commissioners on the Board. The Fire District has a myriad of statutory responsibilities including the levying of taxes for the purpose of providing fire protection for the residents of the District. The Fire District budget is used to provide the Chappaqua Fire Department the funding necessary for equipment, apparatus, training, day-to-day operations, maintenance and repair of District facilities, amongst other specialty matters.

Divider
Construction Update 6.4.25

Secretary CHRISTINE DENNETT, June 04

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates

Progress and Coordination
• Excavation equipment has been mobilized and soil removal is underway.
• Block work is in progress in preparation for the precast mezzanine installation.
• A crane and steel installation crew will begin installing the precast mezzanine deck, which is expected to take approximately two ... (Full Story)


Divider
Construction Update 5.27.25

Secretary CHRISTINE DENNETT, May 27

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates

Progress and Coordination
• Excavation equipment was mobilized today, and soil removal is scheduled to begin on Wednesday, 5/28.
• Block work is underway and expected to be completed this week in preparation for the upcoming precast mezzanine installation.
• A crane and steel installation crew are scheduled to ... (Full Story)


Divider
Construction Update 5.19.25

Secretary CHRISTINE DENNETT, May 19

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates

Progress and Coordination

Masonry Work (Updated!)
Block work will continue throughout the week, with masonry teams fully mobilized on site. The mason has started work on the southwest portion of the project, near the elevator, fill station, and shower area.

Mechanical, Electrical, Plumbing, and Fire Protection ... (Full Story)


Divider
No Caption Construction Update 5.14.25

Secretary CHRISTINE DENNETT, May 14

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates

Progress and Coordination

Steel Installation (Updated!)
Steel erection is progressing steadily, officially taking the project vertical. This week, crews are focusing efforts on the west side of the project, working on completing bolted connections between steel beams and columns, installing metal decking on the ... (Full Story & Photos)

Divider
Construction Update 5.7.25

Secretary CHRISTINE DENNETT, May 07

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates:

Progress and Coordination:
• Steel Installation (Updated!):
Steel erection is underway, officially taking the project vertical. Work includes fall fittings, completing bolted connections between steel beams and columns, installing metal decking, and ensuring all beams are level.
• Masonry Work (New!):
The mason ... (Full Story)


Divider
No Caption Construction Update 4.30.25

Secretary CHRISTINE DENNETT, April 30

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates:

Progress and Coordination:

•Crane & Steel Installation (New!):

Exciting milestone — the crane has been delivered, and the first steel has been installed, officially taking the project vertical! Steel erection, including fall protection fittings, will continue on the west side of the site.

•Masonry Work (New!):

Masonry ... (Full Story & Photos)

Divider
Construction Update 4.22.25

Secretary CHRISTINE DENNETT, April 22

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates:

Progress and Coordination:

Plumbing Work:

•Backfilling the plumbing pipes with stone in all areas where electrical conduits are not being installed.

Electrical Work:

•Installation of the electrical conduit is scheduled to begin. An inspector is confirmed to be onsite tomorrow, Tuesday, 04/23 at 9:30 AM, to ... (Full Story)


Divider
Construction Update 4.8.25

Secretary CHRISTINE DENNETT, April 08

New Castle Fire District No. 1 Modernization Project Update
Chappaqua, NY

Key Updates:

Progress and Coordination:
• Plumbing Work:
The plumbing work in the laundry and shower rooms has been completed. An inspection was conducted, and the system was successfully pressure tested by the Town. Additionally, a survey of the pipes is currently underway. The surveyor is onsite today, and the survey work ... (Full Story)


Divider

Your feedback is important to us!  Feel free to sign the guestbook.


Website Designed and Hosted By: Content Proudly Maintained By: Contact Info:
Firehouse Solutions
www.FirehouseSolutions.com
New Castle Fire District No.1
491 King Street
Chappaqua, NY 10514
Emergency Dial 911
Non-Emergency: 914-238-6287
E-mail: bofc@ncfd1.org
Copyright © 2025 Firehouse Solutions (A Service of Technology Reflections, Inc.)